Billdr PRO
JP

Basement remodel

James Friday45 West Washington St, Orlando, FL 32801
In construction
Invoices

Total Income

$23,797.96

Total Expenses

$11,441.12

Net Profit/Loss

$12,356.84

Working Capital Available

$75,000

Pre-approved based on your project pipeline ยท Funded in 24hrs

Apply NowPowered by Slate
CategoriesForecastIncomeExpensesProfit
General conditions$7,000.00$7,000.00 (100%)-$6,500.00$500.00
Demolition$3,200.00$2,000.00 (62.5%)-$1,000.00$1,000.00
Framing & Structural$12,500.00$1,602.52 (12.8%)-$1,541.12$61.40
Electrical$8,400.00$1,000.00 (0%)-$2,400.00-$1,400.00
Plumbing$6,800.00$0.00 (0%)$0.00$0.00
Drywall & Paint$5,200.00$0.00 (0%)$0.00$0.00
Flooring$4,500.00$0.00 (0%)$0.00$0.00
Total$47,600.00$11,602.52-$11,441.12$161.40